Brightview Innovation Center Update | October 8, 2021
MC recently conducted a site visit at Brightview Innovation Center in Herndon, Virginia to review the construction progress. Donohoe Construction Company is currently erecting joists and setting formwork for the Hambro slab at Level 5. Once complete, the building will consist of 6 levels of Hambro slab supported by a two-way flat plate at Level 2 for a total of 7 framed floors. The engineers at MC enjoy being hands on and making visits to active construction sites to see our designs come to life. We pride ourselves on being contractor friendly and are always working towards continuing to provide the most efficient designs for construction.