GAF Site Expansion Milestone! | July 7, 2022
Two weeks ago, the structural steel framing was starting to be placed over S. Newkirk Street for the bridge connecting a new and existing GAF distribution warehouse in Baltimore City. The new bridge truss is composed of WF and HSS members to support the roof, floor, and walls of the bridge. Over the past couple weeks, the steel columns and trusses, and the metal floor and roof deck have been installed. Light gauge wall framing is currently underway. Once completed, the bridge will support two conveyors and be wide enough to accommodate three aisles for personnel. MC is proud to have partnered with Urban Design Group, B&R, Kimley-Horn, and Chesapeake Contracting Group on this project.